Substrate & preparation
The concrete roof area was prepared and primed before the waterproofing build-up began.
COMPLETED WATERPROOFING PROJECT
A documented waterproofing sequence from concrete substrate and primer through reinforcement, hot melt application, insulation and stone ballast finish.
PROJECT SEQUENCE
Follow the installation in order, from substrate preparation to the protected roof finish.
The concrete roof area was prepared and primed before the waterproofing build-up began.
Fleece reinforcement was formed around parapets, upstands, outlets and penetrations.
The reinforced waterproofing layer was applied continuously across the flat area and details.
Insulation boards were coordinated across the flat area and continued into the perimeter details.
A stone ballast finish completed and protected the waterproofing build-up.
Deliver a coordinated waterproofing build-up around parapets, penetrations and upstands on a live residential development.
Prepare and prime the concrete, reinforce the field and upstands, apply the hot melt build-up, install insulation and complete the roof with a stone ballast finish.
A complete protected roof build-up with coordinated upstands, penetrations and finished perimeter details.
SITE GALLERY
Select any photograph to see the waterproofing details at a larger size.
MORE SITE WORK
Additional flat roof and parapet waterproofing details supplied from completed and in-progress work.